2014 Gayhurst School

Feasibility Study and Construction Project to resurface the school sports grounds comprising on cricket table and two junior football pitches including installing topsoil on site to increase safety, limited drainage and minor re-contouring of surface levels (before and after shots below).

Contractor: Agripower. Project Cost: c.£76,000.

Before:

2014 Gayhurst School

After:

2014 Gayhurst School